What are the three phases of the Construction Quality Management Program (CQM)?

Disable ads (and more) with a premium pass for a one time $4.99 payment

Prepare for the Seabee Combat Warfare (SCW) Exam with engaging flashcards and multiple choice questions, each accompanied by helpful hints and explanations. Enhance your readiness and confidence!

The three phases of the Construction Quality Management Program (CQM) are Preparatory, Initial, and Follow-up. This structured approach is essential for ensuring the quality of construction work and involves a detailed process for managing quality throughout a project.

The Preparatory phase focuses on preparatory meetings and planning efforts that set the foundation for quality management. This involves reviewing contract documents, defining quality standards, identifying potential issues, and ensuring that all stakeholders understand their responsibilities.

The Initial phase takes place when construction begins. This phase involves the implementation of the quality management plan, with inspections and monitoring to ensure that work is progressing as per the specified standards. It allows for timely adjustments and interventions if any quality issues arise.

The Follow-up phase occurs throughout the construction project and involves ongoing assessments and audits to ensure continuous compliance with quality standards. It is crucial for maintaining quality, tracking progress, and making necessary adjustments to improve performance.

By adhering to these three phases, project managers and teams can systematically manage quality and performance, ultimately leading to successful project outcomes.